Dear Resident:
The Town of Lockport has contracted with 4th Generation Construction of Niagara Falls, New York to perform the waterline replacement on Beattie Avenue. The project includes 8,200 linear feet of waterline replacement on the east side of Beattie Avenue between Dysinger Road and Lincoln Avenue. The anticipated construction dates of this project are as follows:
• Begin Construction: Late March 2023 (Estimated)
• All work complete November 2023
In the meantime, if you have any questions or concerns, feel free to contact our office at 716-688-0766. We thank you for your cooperation while the Town completes this work.