September 2023 Niagara County Department of Public Works Beattie Avenue Culvert Work
Good day,
Below is the revised Beattie Avenue Culvert schedule provided to me through NCDPWD from the contractor as of last Frida, September 5.
Set Up Message Board 8/28/23
Close the Culvert/Road & Remove Old Culvert 9/5/23
Install New Culvert 9/6/23 through 9/18/23
Install Pavement, Shoulder, Turf, Striping 9/18/23 through 9/22/23
Open Culvert 9/25/23 (Monday)
The contractor is responsible for coordinating with fire, police, garbage, the school bus garage, etc. on this road closure.
If any residents have any concerns/complaints, etc., please note that this is a Niagara County Department of Public Works project and not a project by the Town of Lockport.
Any questions can be directed to Eric Stein at NCDPW at 716-439-7260 or eric.stein@niagaracounty.com. Updates will be posted as we get them.
Robert D. Klavoon, PE (NY, CT, AZ)
Senior Civil Engineer, Principal
RESIDENTS, PLEASE BE PATIENT, THE WORK WILL BE COMPLETED AS SOON AS POSSIBLE.
Please be alert to work zone traffic rules!